Estimated Remodeling Timelines
At Caine + Co. we believe in transparency and proactive communication. Below are the typical project durations for the luxury home renovations we showcase throughout Scottsdale and Paradise Valley. Timelines are estimates and may vary based on project complexity, permitting, and client selections.
Check out our table below for estimated project timelines based on historical data.
Project Type | Estimated Total Timeline |
---|---|
Full Home Renovation | 6–9 months |
Kitchen Remodel | 10–16 weeks (2.5–4 months) |
Primary Bathroom Remodel | 8–12 weeks (2–3 months) |
Guest Bathroom Remodel | 6–10 weeks (1.5–2.5 months) |
Outdoor Living Remodel | 10–16 weeks (2.5–4 months) |
Casita / Guest House | 4–6 months |
Custom Walk-In Closet | 4–6 weeks (1–1.5 months) |
Grand Entryway Update | 4–8 weeks (1–2 months) |
What to Expect
- All timelines include design, permitting, and construction phases.
- Material selections, HOA approvals, and scope changes may impact duration.
- We provide a detailed, customized schedule at contract signing for every project.
For a more tailored estimate schedule a consultation with our team.